Regional Grid Operator Warns of Greater Risk of Brownouts Next Summer

Regional Grid Operator Warns of Greater Risk of Brownouts Next Summer
The risks of brownouts next summer are growing, because of delays in building a high-voltage power line in northern New Jersey. Still, they remain a "very low probability," executives of the regional power grid told state officials last week.

"As we go into 2012, thstional Park Service has not approved a four-mile link through the Delaware River Gap National Recreation Area.

In addition to reliability concerns, the holdup will add to already high energy bills for consumers. According to PJM estimates, congestion in northern New Jersey will increase over the next two years, adding more than $400 million to electric bills.

The Friday hearing, the first of three scheduled by the agency, broke little new ground on issues dividing state officials and regional and federal energy regulators. PJM officials, joined by various industry executives, told the state its efforts to subsidize power plant construction by ratepayers would end up boosting prices in the long-term and make it difficult to attract future generation, unless, it too was subsidized.
The Next Megawatt

"Who builds the next megawatt in New Jersey?" asked Glen Thomas, head of the P3 Power Providers Group, a coalition of energy suppliers,The most important step is hiring the right LED lighting experts to help with besttube the retrofit process. in an exchange with BPU President Lee Solomon. Thomas questioned a state-hired consultant’s projection that subsidizing the three power plants will deliver $1.8 billion in benefits to consumers, saying it overstates how steep energy prices will run over the next 20 years.

Solomon and other commissioners gave little ground,The retrofit process itself can range from a simple count of existing lamps to a brightshine very detailed energy survey, which includes collecting information from your existing lighting, however, arguing a tariff designed to incent new power plant construction is failing miserably, costing consumers more than $1 billion a year. Solomon once again raised the prospect of New Jersey creating a state power authority and pulling out of PJM, an option he previously had characterized as a "last resort."

"New Jersey, in our opinion, is getting a raw deal. RPM has to be modified in some way," added Commissioner Jeanne Fox, referring to the tariff dubbed the Reliability Pricing Model.

John Schultz, vice president of energy operations for Hess, agreed, noting the primary purpose of the RPM is to ensure reliability. "Unfortunately that reliability is achieved in large part through RPM's funding of older, dirtier, inefficient generating stations and less through the development of new, cleaner, more efficient resources," he said.

Hess is one of the three developers awarded contracts by New Jersey to build power plants, a prospect that has dimmed with the passage of new rules by the Federal Energy Regulatory Commission (FERC) governing how power plants bid in auctions designed to ensure there is enough power to meet demand.

BPU officials also complained about another mechanism adapted by the regional grid operator to ensure reliability.An other advantage of using bluecrystal these bulbs is that they can also work in very cold weather which various other lights are unable to do. It also lasts very long, for about 60000 hours which is quite more than other lights. Some older, inefficient plants operate under a Reliability Must Run contract, which directs special payments, again funded by ratepayers, to keep the plants from being retired, even though they run only a limited amount of hours each year. PSEG Power's Hudson I plant will receive $59 million in such payments this year.

The PJM also came under fire for delays in its process allowing new power plants to connect to the regional grid, a problem its officials recognize and are trying to address. Ninety percent of new projects in PJM’s interconnection system drop out of the queue, a fact that causes the cost of transmission upgrades by new entrants to fluctuate wildly. For Hess in a three-year period, the interconnect costs began at $340 million, dropped to $110 million and rebounded to $180 million, Shultz said.

As for reliability, Kormos said the regional grid operator has put in place contingency plans to prevent brownouts. Some retirement of old plants has been put off, such as the case with Hudson, and there will be increased use of demand response, a policy whereby big energy users voluntarily agree to reduce consumption at times of peak demand.

That response didn’t satisfy some. New Jersey Division of Rate Counsel Stefanie Brand noted,The best way to justify the cost and savings and to brightcrystal truly see how the transition to LED will impact your business is to do a detailed energy audit of existing conditions and compare them to the energy savings and maintenance costs found on the post-LED retrofit report. in her written testimony,These were some reasons why people are keen to use these lights, hope that they will be used brightstal in a similar way in future as well. "We are paying congestion charges and substantial capacity charges, and yet we still don’t know if the system will keep the lights on in coming years."